In September 2012, we started the lifting in an area of ​​1700m2 of the Cybernetics Office Center building in Warsaw-for its main tenant of Securitas Poland.

The works took place during the afterhours and on the weekends – which required careful planning and meticulous scope of work, keeping to a schedule agreed with the customer.

The scope of work was the exchange of suspended ceilings, the lighting, the SAP system reconfiguration, replacement of carpets, construction works and electrical work associated with the change in the allocation of space, together with the provision of all necessary as-built projects.

Planned completion of the work was in November 2012