In December 2011 our company completed all works on the rearragement of reception hall and adjacent rooms for Sygnity company, based in Kopernik A office estate, which was done on a space of 230 m2.
Scope refurbishment included redevelopment of HVAC installation, exchange of all floor covers for PVC/ceramic, tiles/carpets tiles, exchange of lighting, redevelopment of bathrooms and installations of new access control gates. The largest endeavour of this project was the time scheduled for realisation – works began on the 8th of November, 2011 and were finished on the 5th of December, 2011. More pictures in “Realisations” folder.